Construction of Kertajati Airport reaches 64.2%

Bandara-Silangit-Tapanuli-Utara.jpg

Kertajati Airports construction project in Majalengka, West Java, comprising access, drainage, interchange ramp, and parking lots has reached 64.2% on Jan 29, PT. Bandarudara Internasional Jawa Barat Director Virda Dimas Ekaputra stated.

The construction of the Kertajati Airport comprises three working packages, Ekaputra noted.

Package 2 encompasses the construction of the main passenger terminal building in cooperation with PT. Wijaya Karya and PT. PP, with a contract value of Rp1.39 trillion.

Meanwhile, Package 3 comprises the construction of facilities for supporting operations, such as a cargo terminal and regional electrical connection by PT. Waskita, with a contract value of Rp416 billion.

“The work on Package 2 has reached 19.94%, while that on Package 3 has reached 35%,” Ekaputra stated.

Hence, he noted that the overall progress of the Kertajati airports construction project has reached 30% on February 5, 2017.

Ekaputra pointed out that the cost for Phase 1 reaches Rp2.1 trillion of the total development investment of Rp4.5 trillion.

He expressed optimism that the infrastructure work would be completed on July 3, 2017; the building to support operations on August 8, 2017; and the terminal building on December 6, 2017; while the initial operations will begin in January 2018 and full operations in March 2018.


About Retail News Asia

Retail News Asia is committed to providing local and global retailers with the latest news from the Asian retail market on a daily basis.

We have resources for everyone from independently owned business owners to online-only retailers and major chains expanding their reach throughout the Asian market. Retail News is “the news source” with over 50 weekly posts and 13,6 million readers.


CONTACT US

CALL US ANYTIME

Most read



Retail updates

Stay up to date of the lates updates and retail news from Asia.








X