Wind power developers race to complete projects for incentive price

By Rajiv Menon
2 min read
Wind power developers race to complete projects for incentive price
Wind power developers race to complete projects for incentive price

Listen to this article

0:00 / 0:00
In this article (5)

Investors in wind power projects are racing to complete construction this month to enjoy an incentive feed-in tariff, but face procedural hurdles and those caused by Covid-19.

This month the developer of a plant in Quang Tri Province is rushing to complete construction and begin test runs, but is being slowed down by the various administrative procedures they have to go through.

The chairman of the investing company, who asked not be identified, said the plant needs to operate at least 70 percent of capacity, which means when the wind is weak this cannot be done.

“We made much effort but the test depends on the weather.”

To encourage renewable energy, Vietnam will give wind power projects that begin operation before Nov. 1 a feed-in tariff of 9.8 U.S. cents per kilowatt-hour to offshore projects and 8.5 U.S. cents for onshore ones. The tariff lasts 20 years.

But of the 106 wind power farms that have registered to provide 5,655.5 megawatts of power, there were only six that have received an operational permit by the end of last month.

Developers complain about the large number of permits they need to acquire to start the project, for example, the fire safety permit, and there are many unexpected challenges that lie ahead in getting these permits.

“We won’t be relaxed until the final permit is given, as from now until it is difficult to anticipate what will come up,” the chairman in Quang Tri said.

He proposed that the Department of Planning and Investment in the province increase the work hours of its employees, even at night, to support developers in acquiring permits. Several challenges contributed to a construction delay.

Some developers said that the fourth Covid-19 wave slowed their projects by two months, as experts were unable to enter the country, while the transportation of equipment faced blockages as authorities tightened social distancing.

Hoang Ngoc Quy, CEO of a developer HBRE, has been letting workers take three shifts to work 24 hours a day in the last three days.

He proposed that the government provides incentive policies, especially in loans, to support wind power farms.

The best support to extend the deadline until December next year for onshore projects and December 2025 for offshore projects.

Vu Chi Mai, head of component for renewable energy and energy efficiency at the German Agency for International Cooperation (GIZ), said that Covid-19 caused unexpected impacts on the projects, and therefore the deadline should be pushed back three to six months.

Ha Dang Son, deputy director of the Vietnam Low Emission Energy Program, said that the extended deadline should be given to certain projects depending how severe the Covid-19 impact was, not to all projects, as some have not even started.

Questions & Answers

Q.

What incentive is driving wind power developers to complete their projects by the end of the month?

A.

Developers are racing to meet a November 1 deadline to receive an incentive feed-in tariff. This tariff offers 9.8 U.S. Cents per kilowatt-hour for offshore projects and 8.5 U.S. Cents for onshore projects, lasting 20 years.

Q.

What are the main obstacles faced by wind power developers trying to meet the deadline?

A.

Developers face significant procedural hurdles, including a large number of permits required, with unexpected challenges in obtaining them. Also, the fourth Covid-19 wave caused delays due to expert travel restrictions and equipment transportation blockages.

Q.

How many wind power farms have received operational permits so far, compared to those registered?

A.

Out of 106 wind power farms that registered to provide 5,655.5 megawatts, only six had received an operational permit by the end of last month. This indicates a significant bottleneck in the approval process.

Q.

What solutions have industry leaders proposed to address the current challenges?

A.

Some proposed extending the deadline, with suggestions ranging from three to six months to December next year or December 2025. Others suggested increasing work hours for provincial employees and providing incentive policies, particularly loans.

Weekly Briefing

Asia's retail intelligence, in your inbox

One email a week: the retail stories, numbers and moves that mattered across Asia. Nothing else, and you can unsubscribe in one click.

  • Top industry moves and market shifts
  • Weekly data-driven analysis from across Asia
  • Every Monday morning, one email only

Read by retail operators, investors and brand teams across Asia.

Protected by a quick human check. No spam, ever. Unsubscribe in one click.

SecureGDPR ready